Last Up-Dated 10/07/04

 

Mini Presentation Aerial Photos

Building Occupancy: Lectures and Labs
January - April, 2004

Opening Ceremony March 26, 2004

General Information (Plans)

 

Models Summer-Fall 02
Site Preparation/Foundation
February - June 12

 

Building Takes Shape
Structural Steel
May 22 - June 12
Steel Decking Installed and
Concrete Poured
June 21 - July 12
       

Lecture Hall, Concrete Blocks and Internal Structure
July 23 - August 26

Internal and External
Construction Continues
August 27 - September 24

       
Alumni Board Tour,
Construction Continues
September 28 - October 31
CP Lecture Theater, Roofing,
Hokie Stone - Construction Continues

November 1 - December 22
       
Outside Stone, Windows, Air Handling, Dry Wall - Construction Continues
January 1 - January 31
Hokie Stone, Windows, Dry Wall, etc. Construction Continues
February 1 - February 20
       
Hokie Stone Rises Even Higher -
Inside
Construction Continues
March 1 - March 31
Hokie Stone Rises To The Roof -
Inside
Construction Continues
April 1 - April 30
       
Labs Continue To Take Shape -
Construction Continues
May 1 - May 31
The Outside Takes On A New Look-
Construction Continues
June 1 - August 29
       
The Outside Takes On A Finished Look-
Construction Continues
September 1 - November 24

Welcome to the Finished
Chem/Physics Building

CountZ.com
CountZ.com